Upgrading of E/M Works for the Wastewater Pumping Stations of Ialyssos

Πίσω

Upgrading of E/M Works for the Wastewater Pumping Stations of Ialyssos

On 26th of November, 2024, JV MICHANIKI PERIVALLONTOS S.A. – STIRIXIS TEXNIKI signed a contract with the Municipal Water and Sewerage Company of Rhodes for the construction of necessary works to upgrade the existing wastewater pumping stations in the Municipal Unit of Ialyssos, with a total value of 3.374.960,90€. The duration of the contract is 60 months, of which the first twenty-four (24) months are dedicated to the construction of the project, the next twenty-four (24) months concern the technical supervision of operations, and the remaining following twelve (12) months to its optional operation period.